Subject: Заказы на изменение В этом абзаце речь идет о заказах на изменение по определенным видам работ. Никак не могу перевести последнее предложение... Помогите, пожалуйста!!!"We accept the principle of a variation to the complete work of point 1.1. However, the figure 25 % needs further explanation. This could be for example a refence to man-hours spent or time consumed compared to a full completion of the work. Furthermore, the cost of this VOR should be zero, since only part of the already approved budget of Exhibit B will be used. THIS VARIATION ORDER HAS ONLY A REDUCED COST CONSEQUENCE FOR THE CONTRACT." |