Subject: по поводу контрактов с возмещением затрат К чему относятся 70-80% в: Sellers are normally obligated to notify the buyer in advance if they anticipate exceeding the authorized funding levels, typically set at about the 70% to 80% point of contract value. К тому, что превышение на 70-80% (неужели можно настолько превышать?!), или к тому, что уведомлять надо, когда сделал уже 60-80% от стоимости контракта и понял, что превысишь?Это предпоследняя фраза в следующем контексте. Under the cost reimbursable type contract the seller's obligation is merely to provide a "best efforts" commitment to complete all of the work as stipulated in the contract. If the seller incurs all of the costs as authorized in the contract, but does not finish the entire scope of work, the seller cannot be sued for the difference. Their legal commitment is to provide their best effort only to finish the job.However, the buyer must fund the entire job to its completion, to the limit of their contractual arrangement. Sellers are normally obligated to notify the buyer in advance if they anticipate exceeding the authorized funding levels, typically set at about the 70% to 80% point of contract value. Once notified, the buyer must decide whether or not to continue to fund the job, or to terminate the effort.
|