Subject: stand-by case law
Здравствуйте! Подскажите, пожалуйста, как возможно перевести данное словосочетание!

In case the stand-by case is for a duration less than a day, the stand-by rate shall be calculated pro-rata temporis.

Спасибо заранее большое!

 V

link 20.07.2006 9:57 
контекст

 urusal

link 20.07.2006 10:03 
а выше про Weather Days...

It is understood that climatic conditions that prevent the recording crew from working will be agreed upon by COMPANY'S Representative and CONTRACTOR’S Party chief, such agreement not to be unreasonably withheld.
In case the stand-by case is for a duration less than a day, the stand-by rate shall be calculated pro-rata temporis.

 V

link 20.07.2006 10:36 
это не контекст

шире загребайте

обчно стэнд-бай - это когда подрядчик / "оказыватель услуг" :-) и т.п. не выполняет собственно работы, но находится "на дежурстве, на приколе", на случай, если вдруг жахнет и он понадобится Заказчику.

В ООН, например, - когда синхронист "на стендбае" (а узнаёт он об этом накануне, прослушивая программу следующего дня по телефону-автомату), это значит, что он должен не приходить в ООН, но находиться в пределах телефонной досягаемости и не более чем 30-минутной готовности прибыть на работу.

так вот, похоже, в Вашем тексте за день стендбая ему платят такие-то вот ставки.

Для разряжения ситуации:
Стишок 20-летней давности. Стих женевских синхронистов.

Вот сижу я на диване,
Пиво попиваю.
Что-то в ж* зачесалось,
Значит, быть стендбаю
(с)
Лёни Швецова

 urusal

link 20.07.2006 11:15 
:-))))Да рассмешили своим стишком!!!!!Спасибо))))))Может этот, так называемый, стэндбай - просто написать, как неблагоприятные климатические условия...

Ну, а если, шире загрести))то вот:Многовато получилось))

Standby Rates

Recording Crew (3-D) excluding dozing crew
A daily fee of: UAH XXXXXX
Dozing crews

Except as expressly provided otherwise, the Standby Rates shall only apply under the following conditions:

2.6.1 COMPANY requested crew standby, except when CONTRACTOR’S equipment is not meeting specifications.

2.6.2 Lack of COMPANY provided program.

2.6.3 Local Government mandated shutdown, force majeure events and cases and other acts not attributable to fault of CONTRACTOR.

2.6.4 Weather Days . The Standby Rate for Weather (herein so called) shall apply under the following conditions:

Weather Days are defined as periods when the recording crew is unable to work for one (1) hour or more, during daylight hours within an operational day, due to climatic conditions such as heavy rains, high wind or flooding but excluding static induced noise within the seismic instrumentation. It is understood that climatic conditions that prevent the recording crew from working will be agreed upon by COMPANY'S Representative and CONTRACTOR’S Party chief, such agreement not to be unreasonably withheld. In case the stand-by case is for a duration less than a day, the stand-by rate shall be calculated pro-rata temporis.

 D-50

link 20.07.2006 11:15 
+ еще может быть простой в работе.

У нас например есть такая разбивка тарифов

Standard
Stand-by
Stand-by caused by Company

 10-4

link 20.07.2006 13:21 
Здесь: простой по вине заказчика (подрядчик готов начать работы, а заказчик не обеспечил то, что должен был по контракту обеспечить, или какие другие независящие от подрядчика причины возникли, иногда технологического свойства)

 